PeopleCert PRINCE2 Agile Practitioner Exam Questions - Navigate Your Path to Success

The PeopleCert PRINCE2 Agile Practitioner Project Management (PRINCE2 Agile Practitioner) exam is a good choice for Prince 2 Agile Practitioners and Project Managers and if the candidate manages to pass PeopleCert PRINCE2 Agile Practitioner Project Management exam, he/she will earn PeopleCert Project, Programme and Portfolio Management Certification. Below are some essential facts for PeopleCert PRINCE2 Agile Practitioner exam candidates:

  • TrendyCerts offers 50 Questions that are based on actual PeopleCert PRINCE2 Agile Practitioner syllabus.
  • Our PeopleCert PRINCE2 Agile Practitioner Exam Practice Questions were last updated on: Apr 22, 2025

Sample Questions for PeopleCert PRINCE2 Agile Practitioner Exam Preparation

Question 1

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

PRINCE2 Agile Practitioner Exam Question 1 Exhibit 1

Staff Training - Additional information

The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that:

A . the event is carried out safely and professionally;

B . staff members are able to give advice on health and fitness.

This is covered by four work packages:

1. Training syllabus:

* High-level design of the manual.

* Content of each module.

2. Course content for safety and professionalism:

* Detailed design of two modules:

* Health and Safety including basic first aid.

* Customer relations to look after people attending the event.

* Piloting the modules with a group of volunteers.

3. Course content tor giving advice on health and fitness:

* Detailed design of two modules:

* Exercise fundamentals including how to warm up and cool down.

* Healthy eating including what types of food are good for you.

* Piloting the modules with a group of volunteers.

4. Training delivery:

* Production of the training manual;

* Delivery of the training to the rest of the volunteers.

The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile.

Using the Project Scenario and Staff Training Additional information, answer the following question:

The Staff Training Team have developed the following user story:

'As the LGA, I want all volunteers to have received mandatory health and safety training so that we can ensure that the event takes place in a safe environment for the public.'

Which reason explains why the team should deliver the user story in accordance with the 'be on time and hit deadlines' target?

Correct : B

Timely delivery of the health and safety training is crucial to ensure that all volunteers are adequately prepared before the event. Meeting this deadline is essential for ensuring a safe environment for the public during the football tournament, making it a priority to adhere to the schedule.


Options Selected by Other Users:
Question 2

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

PRINCE2 Agile Practitioner Exam Question 2 Exhibit 1

Staff Training - Additional information

The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that:

A . the event is carried out safely and professionally;

B . staff members are able to give advice on health and fitness.

This is covered by four work packages:

1. Training syllabus:

* High-level design of the manual.

* Content of each module.

2. Course content for safety and professionalism:

* Detailed design of two modules:

* Health and Safety including basic first aid.

* Customer relations to look after people attending the event.

* Piloting the modules with a group of volunteers.

3. Course content tor giving advice on health and fitness:

* Detailed design of two modules:

* Exercise fundamentals including how to warm up and cool down.

* Healthy eating including what types of food are good for you.

* Piloting the modules with a group of volunteers.

4. Training delivery:

* Production of the training manual;

* Delivery of the training to the rest of the volunteers.

The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile.

Using the Project Scenario and Staff Training Additional information, answer the following question:

The project product description for the sports event includes the following acceptance criteria (AC):

* It must be possible for the training materials to be maintained in the future by the LGA training department.

* The training materials must be usable for future events run by the LGA.

Which reason explains why the team manager should protect the level of quality in relation to the acceptance criteria?

Correct : C

Ensuring that the acceptance criteria are met is crucial for maintaining the quality of the training materials. This not only affects the usability for future events but also impacts the long-term cost of ownership, as high-quality materials will require less maintenance and adaptation over time. Protecting quality helps ensure that the investment in the training materials is justified and sustainable for future use.


Options Selected by Other Users: