1. Home
  2. SAP
  3. SAP Certified Associate
  4. C_WZADM_01 Exam Info

SAP C_WZADM_01 Exam Questions - Navigate Your Path to Success

The SAP Certified Application Associate - SAP Build Work Zone - Implementation and Administration (C_WZADM_01) exam is a good choice for business associate for business planning consultants and if the candidate manages to pass SAP Certified Application Associate - SAP Build Work Zone - Implementation and Administration exam, he/she will earn SAP Certified Associate, SAP Build Work Zone - Implementation and Administration Certifications. Below are some essential facts for SAP C_WZADM_01 exam candidates:

  • In actual SAP Certified Application Associate - SAP Build Work Zone - Implementation and Administration (C_WZADM_01) exam, a candidate can expect 60 Questions and the officially allowed time is expected to be around 120 Minutes.
  • TrendyCerts offers 60 Questions that are based on actual SAP C_WZADM_01 syllabus.
  • Our SAP C_WZADM_01 Exam Practice Questions were last updated on: Mar 03, 2025

Sample Questions for SAP C_WZADM_01 Exam Preparation

Question 1

What must you do to implement SAP Build Work Zone, advanced edition in a multi-tier landscape?

Correct : C

To implement SAP Build Work Zone, advanced edition in a multi-tier landscape, you would need to create subscriptions in separate SAP BTP subaccounts.

The advanced edition of SAP Build Work Zone allows for multi-tenancy, which means that different teams or departments within an organization can have their own separate Build Work Zone environments. To achieve this, each team or department would need its own subscription in a separate SAP BTP subaccount.

By creating separate subaccounts, each team can have their own isolated development environment, which can help ensure that changes made in one environment do not affect other teams. Additionally, this can help with managing resources and access controls, as each subaccount can have its own set of permissions and resources allocated to it.

Therefore, the correct answer is D - Create subscriptions in separate SAP BTP subaccounts.


Options Selected by Other Users:
A :
0 Votes 0%
B :
0 Votes 0%
C :
7 Votes 70%
D :
1 Votes 10%
Question 2

In which SAP Activate phase are the tasks of the cutover plan executed?

Correct : D

The tasks of the cutover plan are executed in the 'Deploy' phase of SAP Activate. The Deploy phase includes activities such as final preparation, cutover, and go-live support. During the cutover activity, the system is moved from the development environment to the production environment, and the business processes are migrated to the new system. The cutover plan outlines the steps that need to be followed during this process, such as data migration, system testing, and user training.


Options Selected by Other Users:
A :
1 Votes 10%
B :
0 Votes 0%
C :
0 Votes 0%
D :
10 Votes 100%